Construction update – 9th July 2021

Jul 9, 2021Construction Updates

This week we have completed the following works on the individual blocks:

Block C:

  • Decking laid for level 4

Block D1:

  • Decking laid for level 10
  • Vertical columns constructed level 10 to 11

Block D2:

  • Concrete poured for level 12
  • Vertical columns constructed level 12 to 13

Block E:

  • Decking laid for level 4
  • Installation of mechanical and electrical prefabricated modules in the basement

We have also continued to receive deliveries of the prefabricated mechanical, electrical, plumbing and heating corridor modules for D1 and D2 and prefabricated bathroom pods.