Construction Update – 9th April 2021

Apr 9, 2021Construction Updates

This week we have completed the gantry (the raised steel frame platform) ready for our additional office cabins and welfare areas to be installed this weekend. This will create an on-site canteen to provide more space for the workforce while on their breaks.

We have also carried out the following works on the individual blocks:

Building C:

  • Columns have been erected on C1 and C2
  • Decking has been laid for level 1 on C2

Building D1

  • Concrete has been poured on level 4

Building D2

  • Decking has been laid for level 7

Building E

  • Concrete has been poured for the lift core and walls
  • Decking has been laid for level 1