This week works continued internally in our new onsite cabins and welfare facilities. We have also completed the following works on the individual blocks:
Block C
- Concrete has been poured for level 1 on C1 and C2
- Columns have been erected on level 1 to 2 on C1 and C2
Block D1
- Decking has been laid for level 6
- Concrete has been poured for 2/3 of level 6
- Columns have been erected on level 6 to 7
Block D2
- Concrete has been poured for level 8
- Columns have been erected on level 8 to 9
- Climbing screens have jumped to cover level 10
Block E
- Decking has been laid for level 2