Construction Update – 4th June 2021

Jun 4, 2021Construction Updates

This week we have completed the following works on the individual blocks:

Block C:

  • Decking laid for level 2
  • Concrete poured to a section of level 2
  • Columns erected for level 2

Block D1:

  • Concrete poured to level 8
  • Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules being installed on level 2
  • Lift doors delivered

Block D2:

  • Concrete poured to level 10
  • Columns erected for level 11
  • Prefabricated MEPH modules being installed on levels 2, 3 and 4
  • Hoists in use to level 5
  • Bathroom pods delivered for level 2
  • Blockwork to ground floor being built
  • Installation of temporary lift doors started

Block E:

  • Columns erected for level 3