Construction Update – 30th July 2021

Jul 30, 2021Construction Updates

This week we have completed the following works on the individual blocks:

Block C:

  • Concrete poured for level 5 on C1
  • Decking laid for level 6 on C1
  • Concrete poured for level 4 on C2
  • Cinema steel frame construction continued

Block D1:

  • Concrete poured for level 11

Block D2:

  • Concrete poured for level 14

Block E:

  • Preparations for fa├žade panels to be installed are taking place