Construction Update – 30th April 2021

Apr 30, 2021Construction Updates

This week we continued the internal fit out works in our site office and welfare cabins. We have also completed the following works on the individual blocks:

Block C:

  • Decking laid for level 1 on C1
  • Concrete poured for level 1 on C2
  • Columns have been erected on level 1 of C2

Block D1:

  • Decking laid for level 6

Block D2:

  • Concrete poured for level 8
  • Columns have been erected on level 8

Block E:

  • Decking laid for level 2

 