This week we have completed the following works on the individual blocks:
Block C:
- Decking laid to level 3
- Concrete poured to level 3
Block D1:
- Concrete poured to level 9
- Vertical columns constructed level 9 to 10
- Decking laid to level 10
Block D2:
- First concrete pour to level 12
Block E:
- Decking laid for level 4
We have also completed hoarding works to move the vehicle delivery gate to allow for the cinema steel frame to begin construction in the next few weeks.