This week we continue to settle into our new on-site offices and the canteen opened for the workforce in the welfare area. We have also completed the following works on the individual blocks:
Block C:
- Decking laid for level 2 on C1
- Columns being erected for level 2 on C2
Block D1:
- Concrete poured for level 8
- Columns being erected for level 9
Block D2:
- Concrete poured for level 10
Block E:
- Concrete poured for level 2
Work has also continued on two of the substations which are based around block C with both reaching level 1.