Construction Update – 28th May 2021

May 28, 2021Construction Updates

This week we continue to settle into our new on-site offices and the canteen opened for the workforce in the welfare area. We have also completed the following works on the individual blocks:

Block C:

  • Decking laid for level 2 on C1
  • Columns being erected for level 2 on C2

Block D1:

  • Concrete poured for level 8
  • Columns being erected for level 9

Block D2:

  • Concrete poured for level 10

Block E:

  • Concrete poured for level 2

Work has also continued on two of the substations which are based around block C with both reaching level 1.