This week we have carried out the following works on the individual blocks:
Block C:
- Structural steelwork erected
- Decking laid for level 8 on C1
- Concrete poured for level 6 on C2
Block D1:
- Decking laid for level 13
- Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed
- Façade works
Block D2:
- Decking laid for level 16
- Prefabricated MEPH modules installed
- Façade works
Block E:
- MEPH works in the basement