Construction Update – 25th June 2021

Jun 25, 2021Construction Updates

This week we have completed the following works on the individual blocks:

Block C

  • Decking laid to levels 2 and 3
  • Vertical columns constructed to level 2 to 3

Block D1

  • Decking laid to level 9
  • Concrete started to be poured for a section of level 9
  • Mechanical, electrical, plumbing and heating (MEPH) setting out and installation for level 3

Block D2

  • Decking laid to level 12
  • Sipral delivered brackets for level 2, 3 and 4 with installation from Monday. Sipral are fitting our facade and use a steel framing system (SFS) technique where facade panels can be ‘clipped’ onto the brackets that have been installed on the building
  • MEPH setting out and installation for levels 4, 5 and 6

Block E

  • Concrete poured for stairs
  • Decking laid for level 4
  • Blockwork completed in the basement

We have also had various deliveries for the fit-out installation across the buildings, with a number of our prefabricated bathroom pods ready for installation to blocks D and C. The prefabricated bathroom pods have a number of benefits to the project including less waste and quicker installation, as well as minimising the number of operatives it takes to install whilst also ensuring high quality design. 

 