This week we started internal works on our additional office and welfare cabins that were installed last weekend. We have also completed the following works on the individual blocks:
Block C
- Decking is being laid for level 1 on C1
- Concrete has been poured for the section of level 1 on C2
Block D1
- Concrete has been poured on level 5
Block D2
- Decking laid for level 8
- Concrete columns have been poured
- Screens have been lifted to maintain safety
- Snagging (the process of checking a new building for minor faults that may need rectifying) has been carried out on the ground floor and levels 1 and 2
Block E
- Concrete has been poured for level 1
- Snagging has been carried out in the basement