Construction Update – 23rd April 2021

Apr 23, 2021Construction Updates

This week we started internal works on our additional office and welfare cabins that were installed last weekend. We have also completed the following works on the individual blocks:

Block C

  • Decking is being laid for level 1 on C1
  • Concrete has been poured for the section of level 1 on C2

Block D1

  • Concrete has been poured on level 5

Block D2

  • Decking laid for level 8
  • Concrete columns have been poured
  • Screens have been lifted to maintain safety
  • Snagging (the process of checking a new building for minor faults that may need rectifying) has been carried out on the ground floor and levels 1 and 2

Block E

  • Concrete has been poured for level 1
  • Snagging has been carried out in the basement