Construction Update – 22nd October 2021

Oct 22, 2021Construction Updates

This week, we have carried out the following works on the individual blocks:

Block C:

  • Concrete poured for level 10 on C2
  • Façade works to level 6 on C1 and level 3 on C2
  • Prefabricated mechanical, electrical, plumbing and heating modules installed
  • Hoist climbed to level 9

Block D1:

  • Concrete poured for level 16
  • Façade works to level 11
  • Prefabricated MEPH modules installed to level 11
  • Internal drylining partition walls erected
  • Modular bathroom pods installed to level 10

Block D2:

  • Concrete poured for level 19
  • Prefabricated MEPH modules installed
  • Internal drylining partition walls erected
  • Modular bathroom pods installed

Block E:

  • Steelwork installed to the roof
  • Testing of MEPH appliances in the basement