This week, we have carried out the following works on the individual blocks:
Block C:
- Concrete poured for level 10 on C2
- Façade works to level 6 on C1 and level 3 on C2
- Prefabricated mechanical, electrical, plumbing and heating modules installed
- Hoist climbed to level 9
Block D1:
- Concrete poured for level 16
- Façade works to level 11
- Prefabricated MEPH modules installed to level 11
- Internal drylining partition walls erected
- Modular bathroom pods installed to level 10
Block D2:
- Concrete poured for level 19
- Prefabricated MEPH modules installed
- Internal drylining partition walls erected
- Modular bathroom pods installed
Block E:
- Steelwork installed to the roof
- Testing of MEPH appliances in the basement