Construction Update – 21st May 2021

May 21, 2021Construction Updates

This week our onsite cabins and welfare facilities opened, and we have moved into the new office space. We have also completed the following works on the individual blocks:

Block C:

  • Columns erected for level 2
  • Decking being laid for level 2
  • Concrete poured for ground level

Block D1:

  • Concrete poured to level 7
  • Decking being laid for level 8
  • Columns erected for level 8
  • Safety screens installed to west elevation

Block D2:

  • Concrete poured to level 9
  • Decking being laid for level 10
  • Columns erected for level 10

Block E:

  • Decking being laid for level 2
  • Blockwork loading out for basement works

Work has also continued on the substation which will be used to power the site with the first reaching level 1.