Construction Update – 1st October 2021

Oct 1, 2021Construction Updates

This week we have carried out the following works on the individual blocks:

Block C:

  • Concrete poured for the podium

Block D1:

  • Decking laid for level 14
  • Façade works
  • Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed
  • Bathroom pods delivered ready for installation

Block D2:

  • Concrete poured for level 18
  • Façade works
  • Prefabricated MEPH modules installed
  • Bathroom pods delivered ready for installation

Block E:

  • MEPH works in the basement

 

 