Construction Update – 18th June 2021

Jun 18, 2021Construction Updates

This week we have completed the following works on the individual blocks:

Block C:

  • Decking laid for level 2
  • Concrete poured on level 2
  • Columns erected from level 2 to 3

Block D1:

  • Concrete poured for level 8
  • MEPH (mechanical, electrical, plumbing, heating) prefabricated modules installed

Block D2:

  • Columns erected from level 11 to 12
  • MEPH prefabricated modules installed

Block E:

  • Blockwork in the basement
  • Concrete poured for stair walls from the basement to level 1