Construction Update – 16th July 2021

Jul 16, 2021Construction Updates

This week we have completed the following works on the individual blocks: 

Block C:  

  • Concrete poured for level 4 on C1 
  • Decking laid for level 5 on C1 
  • Columns erected level 4 to 5 on C2 
  • Central area between buildings cleared for steelwork to be erected 

Block D1:  

  • Decking laid for level 10 
  • Mechanical, electrical, plumbing and heating modules installed for level 4 and 5 
  • Bathroom pods delivered for level 4 
  • Safety screens jumped to level 10 

Block D2: 

  • Concrete poured for level 13 
  • MEPH prefabricated modules installed for levels 5 to 8 
  • Blockwork completed on level 0 
  • Brackets for façade panels installed for level 2 

Block E: 

  • Concrete poured for first set of stairs  
  • Concrete poured for level 4 