Construction Update – 16th April 2021

Apr 16, 2021Construction Updates

This week we have seen progress on all of the buildings, with the following works carried out on the individual blocks:

Building C:

  • Columns have been erected on C1
  • Decking is being laid for level 1 on C1 and C2
  • Steel installation for L1 slab started on C2
  • Sub station brickwork has started

Building D1:

  • Decking has been laid for level 5
  • Concrete has been poured for the first section for level 5

Building D2:

  • Concrete has been poured on level 7
  • Columns have been erected on level 7

Building E:

  • Decking has been laid for level 1

 