Construction Update – 14th May 2021

May 14, 2021Construction Updates

This week works continued internally in our new onsite cabins and welfare facilities which are due to be open in the next week. We have also completed the following works on the individual blocks: 

Block C: 

  • Concrete poured to level 1 on C1 and C2 
  • Columns have been erected on level 1 to 2 on C1 and C2 
  • Ground floor podium slab pour 3 complete 
  • Final dig started to Gate 1 for the pile caps  

Block D1  

  • Concrete poured to level 6  
  • Decking complete to Level 7  
  • Blockwork to ground floor (North) commenced  
  • Loading bays have been formed to serve the logistics deliveries  
  • Hoists have been delivered to serve the South elevation  
  • Prefabricated corridor MEP modules delivered for installation to level 2  

Block D2 

  • Concrete poured to Level 9 near to completion 
  • Prefabricated corridor MEP modules installed up to level 4 
  • Install of hoists to D2 started 

Block E 

  • Concrete poured to level 1  
  • Logistical haul road complete 
  • Accommodation cabins set up complete

 The first of the substations which will power the development have also been constructed to the ground floor.