Construction update – 12th March 2021

Mar 12, 2021Construction Updates

This week we continued to pour concrete on buildings D1 and D2, reaching levels 3 and 5 respectively. We are placing rebar (steel reinforcement bars which hold the concrete in place) ready for concrete to be poured for the ground floor on building C1 and vertical columns (which provide support to hold the floors in place) are being erected on building C2 for the pillars to be poured. Works have continued on building E to allow us to pour concrete for the ground floor next week and works are continuing to build the on-site road for deliveries.