This week we have completed the following works on the individual blocks:
Block C:
- Concrete poured for level 6 on C1
- Concrete poured for level 5 on C2
- Steelwork continues to be erected for the cinema
Block D1:
- Concrete poured for level 11 and decking for level 12
- Façade works to level 5
- Mechanical, electrical, plumbing and heating module installation for level 7
- Bathroom pods delivered for level 6
Block D2:
- Decking and first concrete pour to level 15
- Façade works to levels 3 to 5
- MEPH module installation to level 9
- Bathroom pods delivered for level 6
Block E:
- MEPH works to the basement
We have also carried out works to relocate the hoarding.