We have completed the following works on the blocks this week:
Block C
- Concrete poured for level 2
Block D1
- Blockwork to level 0
- MEPH (mechanical, electrical, plumbing and heating) works on level 3
- Concrete poured for level 8
Block D2
- Decking laid for level 11
- MEPH works on levels 2 to 5
Block E
- Decking laid for level 3