Construction update – 11th February 2022

Feb 11, 2022Construction Updates

This week, we have carried out the following works on the individual blocks:

Block C:
• Waterproofing to roofs
• Façade works to C1 and C2 including boarding, brackets and sealing
• Prefabricated mechanical, electrical, plumbing and heating modules installed
• 1st fix M&E elements installed
• Blockwork to plant rooms

Block D1:
• Concrete finishing works
• Façade works to all elevations
• Internal drylining partition walls erected
• Modular bathroom pods installed to level 10
• Internal M&E installation
• Firestopping to penetrations

Block D2:
• Concrete poured for level 26
• Prefabricated MEPH modules installed
• Internal drylining partition walls erected
• Modular bathroom pods installed
• Internal M&E installation
• Firestopping to penetrations
• Unitised cladding installation

Block E:
• Steelwork installed to the roof
• Testing of MEPH appliances in the basement
• Façade installation