Construction Update – 10th September 2021

Sep 10, 2021Construction Updates

This week we have carried out the following works on the individual blocks:

Block C:

  • Decking laid for level 9 on C1
  • Concrete poured for level 7 on C2
  • Steelwork continues to be erected for the podium

Block D1:

  • Decking laid for level 13
  • Façade works
  • Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed
  • Bathroom pods delivered ready for installation

Block D2:

  • Decking laid for level 16
  • Façade works
  • Prefabricated MEPH modules installed
  • Bathroom pods delivered ready for installation

Block E:

  • Steelwork erected on the roof