Construction Update – 7th May 2021

This week works continued internally in our new onsite cabins and welfare facilities. We have also completed the following works on the individual blocks: Block C Concrete has been poured for level 1 on C1 and C2 Columns have been erected on level 1 to 2 on C1 and C2...

Construction Update – 30th April 2021

This week we continued the internal fit out works in our site office and welfare cabins. We have also completed the following works on the individual blocks: Block C: Decking laid for level 1 on C1 Concrete poured for level 1 on C2 Columns have been erected on level 1...

Construction Update – 23rd April 2021

This week we started internal works on our additional office and welfare cabins that were installed last weekend. We have also completed the following works on the individual blocks: Block C Decking is being laid for level 1 on C1 Concrete has been poured for the...

Grangewood joins us at Lewisham Gateway Phase Two

Grangewood has been appointed as the sub-contractor to deliver the brickwork and blockwork for the project. Blockwork is construction using concrete or cement blocks to build a structure. They will be working with us throughout the project on an ad-hoc basis and are...

Out of hours works – 17th and 18th April 2021

We will be carrying out some weekend works on 17th and 18th April between 8am and 6pm. We will be completing the delivery and installation of our welfare and accommodation cabins on site and installing a hoist on building D to aid the transportation of materials to...

Construction Update – 16th April 2021

This week we have seen progress on all of the buildings, with the following works carried out on the individual blocks: Building C: Columns have been erected on C1 Decking is being laid for level 1 on C1 and C2 Steel installation for L1 slab started on C2 Sub station...