Construction Update – 24th September 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for C1 level 9 Concrete poured for level 1 podium Decking laid for C2 level 9 Block D1: Concrete poured for level 13 Façade works Prefabricated mechanical, electrical,...

Construction Update – 17th September 2021

This week we have carried out the following works on the individual blocks: Block C Concrete poured for level 9 on C1 Steelwork erected for the podium Block D1 Concrete poured for level 13 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH)...

Building Facade

Prater and Sipral are continuing well with the façade works on buildings D1 and D2 with the first panels having been installed over the past few weeks. Both Prater and Sipral use off-site construction methods where façade panels are manufactured to design...

Construction Update – 10th September 2021

This week we have carried out the following works on the individual blocks: Block C: Decking laid for level 9 on C1 Concrete poured for level 7 on C2 Steelwork continues to be erected for the podium Block D1: Decking laid for level 13 Façade works Prefabricated...

Construction Update – 3rd September 2021

This week we have carried out the following works on the individual blocks: Block C: Steelwork erected Concrete poured for level 8 on C1 Block D1: Concrete poured for level 13 Decking laid for level 14 Façade works Prefabricated mechanical, electrical, plumbing and...

Construction Update – 26th August 2021

This week we have carried out the following works on the individual blocks: Block C: Structural steelwork erected Decking laid for level 8 on C1 Concrete poured for level 6 on C2 Block D1: Decking laid for level 13 Prefabricated mechanical, electrical, plumbing and...