Construction Update – 22nd October 2021

This week, we have carried out the following works on the individual blocks: Block C: Concrete poured for level 10 on C2 Façade works to level 6 on C1 and level 3 on C2 Prefabricated mechanical, electrical, plumbing and heating modules installed Hoist climbed to level...

Construction Update – 7th October 2021

This week we have completed the following works on the individual blocks: Block C: Concrete poured for level 10 Steelwork erected for the podium Block D1: Decking laid for level 15 Internal partition walls erected Prefabricated mechanical, electrical, plumbing and...

Construction Update – 1st October 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for the podium Block D1: Decking laid for level 14 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed Bathroom pods...

Construction Update – 24th September 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for C1 level 9 Concrete poured for level 1 podium Decking laid for C2 level 9 Block D1: Concrete poured for level 13 Façade works Prefabricated mechanical, electrical,...

Construction Update – 17th September 2021

This week we have carried out the following works on the individual blocks: Block C Concrete poured for level 9 on C1 Steelwork erected for the podium Block D1 Concrete poured for level 13 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH)...

Building Facade

Prater and Sipral are continuing well with the façade works on buildings D1 and D2 with the first panels having been installed over the past few weeks. Both Prater and Sipral use off-site construction methods where façade panels are manufactured to design...