Construction update – 11th February 2022

This week, we have carried out the following works on the individual blocks: Block C: • Waterproofing to roofs • Façade works to C1 and C2 including boarding, brackets and sealing • Prefabricated mechanical, electrical, plumbing and heating modules installed • 1st fix...

Construction update – 11th February 2022

This week, we have carried out the following works on the individual blocks: Block C: • Waterproofing to roofs • Façade works to C1 and C2 including boarding, brackets and sealing • Prefabricated mechanical, electrical, plumbing and heating modules installed • 1st fix...

Construction Update – 22nd October 2021

This week, we have carried out the following works on the individual blocks: Block C: Concrete poured for level 10 on C2 Façade works to level 6 on C1 and level 3 on C2 Prefabricated mechanical, electrical, plumbing and heating modules installed Hoist climbed to level...

Construction Update – 22nd October 2021

This week, we have carried out the following works on the individual blocks: Block C: Concrete poured for level 10 on C2 Façade works to level 6 on C1 and level 3 on C2 Prefabricated mechanical, electrical, plumbing and heating modules installed Hoist climbed to level...

Construction Update – 7th October 2021

This week we have completed the following works on the individual blocks: Block C: Concrete poured for level 10 Steelwork erected for the podium Block D1: Decking laid for level 15 Internal partition walls erected Prefabricated mechanical, electrical, plumbing and...

Construction Update – 1st October 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for the podium Block D1: Decking laid for level 14 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed Bathroom pods...