One Year on Site Celebration

We captured some footage during our event to celebrate one year on site at the Lewisham Gateway project. Hear from some of the team about progress so far in the video below.

Safety Stand Down Event

We had a videographer come down to site during our Safety Stand Down event to capture some highlights of the day. Watch the video below to find out more about the event and why we hold them every year.

Progress on site July 2020 to February 2021.

Since the start of the project in July 2020 we have made significant progress on site. We have: Cleared the site of all underground obstructions Completed piling works Erected four tower cranes Poured concrete on buildings D1 and D2 Basement dug out for building E...

Social value update.

We have had three graduates and three apprentices working with us on site, including two local residents. We train and upskill the workforce in different areas, with two of the apprentices attending an accredited plant marshall course to support their future careers....