Construction Update – 22nd October 2021

This week, we have carried out the following works on the individual blocks: Block C: Concrete poured for level 10 on C2 Façade works to level 6 on C1 and level 3 on C2 Prefabricated mechanical, electrical, plumbing and heating modules installed Hoist climbed to level...

Construction Update – 7th October 2021

This week we have completed the following works on the individual blocks: Block C: Concrete poured for level 10 Steelwork erected for the podium Block D1: Decking laid for level 15 Internal partition walls erected Prefabricated mechanical, electrical, plumbing and...

Safety Stand Down

On Thursday 30th September we held a Safety Stand Down event for the whole project to highlight the importance of health and safety. All site works were stopped for the day and a variety of stalls were set up to engage the workforce, with some of our supply chain...

Construction Update – 1st October 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for the podium Block D1: Decking laid for level 14 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH) modules installed Bathroom pods...