Construction Update – 24th September 2021

This week we have carried out the following works on the individual blocks: Block C: Concrete poured for C1 level 9 Concrete poured for level 1 podium Decking laid for C2 level 9 Block D1: Concrete poured for level 13 Façade works Prefabricated mechanical, electrical,...

Construction Update – 17th September 2021

This week we have carried out the following works on the individual blocks: Block C Concrete poured for level 9 on C1 Steelwork erected for the podium Block D1 Concrete poured for level 13 Façade works Prefabricated mechanical, electrical, plumbing and heating (MEPH)...

One Year on Site Celebration Event

On Friday 3rd September Lewisham Gateway Phase Two hosted an event to celebrate our progress on site over the first year of the project. We welcomed local residents, alongside the project partners, subcontractors, and staff. The event was held at the local Vinothec...

Building Facade

Prater and Sipral are continuing well with the façade works on buildings D1 and D2 with the first panels having been installed over the past few weeks. Both Prater and Sipral use off-site construction methods where façade panels are manufactured to design...

Construction Update – 10th September 2021

This week we have carried out the following works on the individual blocks: Block C: Decking laid for level 9 on C1 Concrete poured for level 7 on C2 Steelwork continues to be erected for the podium Block D1: Decking laid for level 13 Façade works Prefabricated...