Construction Update – 26th August 2021

This week we have carried out the following works on the individual blocks: Block C: Structural steelwork erected Decking laid for level 8 on C1 Concrete poured for level 6 on C2 Block D1: Decking laid for level 13 Prefabricated mechanical, electrical, plumbing and...

Construction Update – 20th August 2021

This week we have completed the following works on the individual blocks: Block C: Steelwork continues to be erected Concrete poured for level 7 on C1 Concrete poured for level 5 on C2 Decking laid for level 6 on C2 Block D1: Concrete poured for level 12 Prefabricated...

Construction Update – 12th August 2021

This week we have completed the following works on the individual blocks: Block C: Concrete poured for level 6 on C1 Concrete poured for level 5 on C2 Steelwork continues to be erected for the cinema Block D1: Concrete poured for level 11 and decking for level 12...