Construction Update – 30th April 2021

This week we continued the internal fit out works in our site office and welfare cabins. We have also completed the following works on the individual blocks: Block C: Decking laid for level 1 on C1 Concrete poured for level 1 on C2 Columns have been erected on level 1...