An introduction to the Lewisham Gateway Phase Two project

Watch our video and listen to senior members of the project team introduce Phase Two of the Lewisham Gateway Scheme. Muse Developments’ Regional Director Mike Auger and Projects Director Chris Coxall, as well members from the Balfour Beatty team, Emilio Gardeta,...

Progress on site July 2020 to February 2021.

Since the start of the project in July 2020 we have made significant progress on site. We have: Cleared the site of all underground obstructions Completed piling works Erected four tower cranes Poured concrete on buildings D1 and D2 Basement dug out for building E...

Social value update.

We have had three graduates and three apprentices working with us on site, including two local residents. We train and upskill the workforce in different areas, with two of the apprentices attending an accredited plant marshall course to support their future careers....